How to Install the Wykamol Black Sump & Pump Kit

Important disclaimer: This guide is provided for general product information and illustration purposes only. It is not a substitute for the manufacturer's Installation and Operating Guidelines. Always obtain and follow the latest manufacturer instructions before installation. Site conditions, drainage requirements and structural considerations must be assessed by suitably qualified professionals. Electrical work must only be undertaken by a qualified electrician.

The Wykamol Black Sump & Pump Kit is a fully automatic pumping station designed to collect and discharge groundwater from cavity membrane drainage systems and surface water from lightwells to a higher-level discharge point.

The system comprises a robust below-ground chamber, an automatic EA31 submersible pump, internal discharge pipework and a locking access cover. A high-level alarm can be installed to provide an audible warning if the water level rises above its normal operating level.

This guide follows the main stages in the manufacturer's installation documentation, including chamber positioning, inlet connections, cable duct installation, discharge pipework, concrete installation, pump fitting, alarm installation and electrical requirements.

View the Wykamol Black Sump Kit at Clever Shield

Wykamol Black Sump Kit showing the polypropylene chamber, EA31 pump and supplied fittings


1. Wykamol Black Sump – System Overview

The Black Sump is designed to receive water collected by a basement drainage system and pump it to a suitable discharge point. The chamber provides a collection point for incoming drainage, while the automatic pump operates as the water level rises.

The manufacturer's installation guide identifies the following main components:

  • Polypropylene sump chamber.
  • EA31 automatic submersible pump with integral non-return valve.
  • 1¼-inch PVC internal discharge pipework.
  • Locking, pedestrian-duty polypropylene access cover.
  • High-level alarm arrangement, where supplied or specified.

The chamber measures approximately 450mm in diameter and 550mm in height. Its inlet positions can be selected to suit the drainage layout, subject to the permitted connection positions shown in the manufacturer's documentation.

Important: The standard access cover is pedestrian-duty. It must not be assumed suitable for vehicle or roadway loading. Any installation in a trafficked area requires an appropriately designed arrangement and suitably rated access cover.

2. EA31 Pump Specifications

The complete single-pump Black Sump kit uses the EA31 automatic submersible pump.

Specification EA31
Power supply 230V, 50Hz
Rated current 1.9A
Motor rating (P2) 180W
Motor speed 2,800rpm
Maximum vertical output 6.8m
Maximum flow rate 2.9 litres per second
Maximum liquid temperature Below 40°C
Discharge connection 1¼ inch
Free passage 10mm
Pump cable length 10m
Impeller type Vortex
Control Automatic

These are the manufacturer's stated pump specifications. Actual flow and delivery performance depend on the discharge head, pipework arrangement and operating conditions.


3. Planning the Installation and Positioning the Chamber

Choose a suitable position for the pumping station before commencing work. Permanent access must be maintained so that the chamber and pump can be inspected, cleaned and serviced safely.

When planning the position, consider:

  • The location and levels of incoming drainage channels and pipes.
  • The position of the discharge connection and route to the discharge point.
  • The location of the cable duct and any alarm equipment.
  • The space required for the reinforced concrete sump.
  • Permanent access for pump removal and routine maintenance.
  • Potential loading from surrounding floors, structures or traffic.

The manufacturer's chamber diagram identifies specific areas where connections are permitted and areas where drilling is not allowed.

Where possible, the manufacturer recommends positioning the inlets and cable ducts on the flat face opposite the discharge connection. Cable ducts should be positioned as high as possible, with the highest inlet below the cable duct. Connections must not be added below the chamber ridge line.

Do not drill or cut the chamber until the permitted connection positions have been checked against the manufacturer's drawings.

4. Constructing the Waterproof Reinforced Concrete Sump

This is a critical part of the installation. The manufacturer's instructions require the Black Sump chamber to be installed within a waterproof reinforced concrete sump. The void surrounding the chamber must be backfilled with concrete.

Although the chamber is robust, below-ground chambers can be affected by flotation and hydrostatic pressure, particularly where groundwater levels are high.

The reinforced concrete sump must be designed to accommodate the chamber and all required connections, including inlets, discharge pipework, cable duct and vent duct.

A structural and waterproofing engineer must be consulted when designing the reinforced concrete sump and its backfill. The design must ensure that prevailing hydrostatic pressures are not transferred onto the chamber.

Do not treat a simple excavated hole, loose gravel bedding or ordinary backfill as an alternative to the manufacturer's specified reinforced concrete installation.

5. Preparing the Chamber and Installing the Inlets

Before permanently installing the chamber, it should be positioned temporarily within the reinforced concrete sump to establish the correct locations for all connections.

  1. Lower the chamber into the reinforced concrete sump and align it with the proposed drainage and service connections.
  2. Mark the required inlet, cable duct, vent and discharge positions.
  3. Remove the chamber from the sump before preparing the connections.
  4. Prepare the chamber openings in the permitted positions shown in the manufacturer's diagrams.
  5. Ensure all connections are square to the chamber so that the rubber seals can form a watertight connection.

The manufacturer describes the following standard inlet arrangements:

50mm wastewater pipe inlet

Connect the floor drainage channel to a 50mm ABS wastewater pipe using a 50mm channel outlet piece. The 50mm pipe then connects to one of the chamber inlet faces using a 50mm rubber wall seal.

The manufacturer's guide specifies a 76mm hole cutter for this 50mm rubber wall seal. The flanged side of the seal should face outwards.

110mm soil pipe inlet

A 110mm outside-diameter soil pipe can be connected to one of the chamber inlet faces using a 110mm rubber wall seal.

The manufacturer's guide specifies a 140mm hole cutter for this connection. The flanged side of the rubber seal should face outwards.

The size and number of inlets required will depend on the drainage layout and project requirements. Check the site plans and manufacturer's instructions before making any openings.

6. Installing the Cable Duct

A cable duct is required to route the pump power cable and any high-level alarm float cable from the chamber.

The manufacturer's guide specifies a 50mm (2-inch) diameter cable duct. This can be constructed using low-pressure ABS waste pipe or high-pressure PVC pipework. A 50mm rubber wall seal can be used to connect the duct to the chamber.

The manufacturer recommends the following:

  • Position the cable duct on a permitted flat face of the chamber neck.
  • Position the duct as high as possible, following the chamber connection diagram.
  • Use sweeping bends rather than tight 90-degree elbows.
  • Where a corner is required, two 45-degree elbows can be used to create a sweeping bend.
  • Install a draw cord through the duct as it is being constructed.
  • Ensure the loose end of the draw cord cannot slip back into the duct.

The draw cord allows the pump and alarm cables to be pulled through the duct during installation.

If cable extensions are required, all electrical connections must be made by a qualified electrical contractor. Suitable cable extension kits are available from the manufacturer.


7. Connecting the Discharge Pipework

The Black Sump is supplied with a male 1¼-inch threaded discharge connection. The manufacturer's recommended arrangement is solvent-welded 1¼-inch PVC Class E pressure pipe.

Never use push-fit fittings in the discharge line. The manufacturer specifically requires the discharge pipework to be solvent-welded.

Recommended connection – 1¼-inch PVC Class E pressure pipe

  1. Apply plenty of PTFE tape to the male thread of the tank connector.
  2. Screw the supplied 1¼-inch PVC PL/TH socket onto the threaded connection.
  3. Prepare and solvent-weld the 1¼-inch PVC Class E pressure pipe in accordance with the manufacturer's pipework instructions.

Wykamol Black Sump discharge pipework diagram showing the recommended 1¼-inch PVC Class E pressure pipe connection

Alternative connection – 32mm ABS low-pressure waste pipe

The manufacturer also describes an alternative connection using 32mm internal-diameter ABS low-pressure waste pipe.

  1. Apply plenty of PTFE tape to the male thread of the tank connector.
  2. Screw the supplied 1¼-inch PVC TH/TH socket onto the threaded connection.
  3. Apply PTFE tape to the thread of the 32mm ABS male iron and screw it into the PVC socket.
  4. Prepare and solvent-weld the ABS low-pressure waste pipe in accordance with the manufacturer's instructions.

The diagram above illustrates both connection arrangements. Select the appropriate option for the installation and follow the complete manufacturer instructions.

8. Positioning and Securing the Chamber

Once the chamber openings and connections have been prepared, the chamber can be installed within the reinforced concrete sump.

  1. Lay wet mass concrete into the base of the reinforced concrete sump to a thickness of 100mm, as specified by the manufacturer.
  2. Carefully lower the chamber onto the wet concrete base.
  3. Ensure that loose debris is not trapped underneath the chamber.
  4. Align the chamber so that the inlets, cable duct, vent and discharge connections are correctly positioned.
  5. Connect the cable duct, vent duct, inlet pipework and discharge pipework using the specified fittings.
  6. While the concrete base is still wet, backfill the space between the chamber and the reinforced concrete sump with wet mass concrete in a single pour.
  7. Pour the concrete evenly around the chamber, ensuring that no voids are left.

Important – ballasting the chamber: During the concrete backfilling process, the chamber must be steadily filled with water to prevent it from floating or moving.

The difference in level between the water inside the chamber and the concrete backfill must remain below 300mm at all times. The chamber must be ballasted with water at the same rate as the concrete backfill is placed.

During the pour, check that the chamber remains vertical using a spirit level across its opening. Also check that it remains at the correct depth and that the connected pipework is not damaged.

Allow the concrete to cure completely before removing the ballast water. The manufacturer specifically states that the water must not be removed until the concrete backfill has fully set.

9. Access Cover and Roadway Installations

Once the concrete has cured and the ballast water has been removed, fit the access cover onto the top of the access shaft so that it is flush with the finished floor level, where appropriate.

The standard cover is pedestrian-duty. Roadway installations require a different arrangement.

The manufacturer's guide describes a roadway installation in which the top of the access shaft is positioned 300mm below the finished cover level. A suitably rated access cover must be incorporated into a reinforced cover slab, designed so that imposed loads are transferred away from the chamber.

The cover slab design is the responsibility of the installer and structural engineer. Do not allow traffic loading to bear directly onto the chamber.

10. Cleaning the Chamber and Installing the Pump

Once the chamber has been installed and the concrete backfill has cured, remove the ballast water as directed by the manufacturer.

Before installing the pump, thoroughly remove all sand, silt, rubble and general construction debris from inside the chamber.

The manufacturer warns that failure to remove sand, silt, rubble and other debris will invalidate the pump warranty.

After cleaning:

  1. Partly refill the chamber with clean water for testing and flushing the discharge pipework.
  2. Connect the internal pipework to the discharge connection using the supplied socket union.
  3. Check that the O-ring is correctly seated within the union before tightening.
  4. Check that the pump float arm can be raised fully and does not catch on the chamber or pipework.
  5. Ensure that the pump is correctly positioned and that the internal pipework is secure.

Wykamol Black Sump chamber with EA31 pump, internal fittings and supplied components

11. Installing the HW-9 High-Level Alarm

The HW-9 is a 9V battery-powered high-level alarm. Its separate mini float switch detects a rising water level within the chamber and activates the audible alarm.

The manufacturer's installation diagram shows the correct arrangement of the EA31 pump, float switch, cable and alarm sounder.

Wykamol Black Sump HW-9 high-level alarm installation diagram showing the EA31 pump, mini float switch, float cable and alarm sounder

Follow the manufacturer's instructions:

  1. Remove the screws from the rear of the alarm sounder module.
  2. Insert a 9V alkaline battery, ensuring that the battery clips are firmly connected. The battery is not included.
  3. Reassemble the alarm housing and secure the screws.
  4. Press and hold the blue test bar for two seconds. The alarm buzzer should sound if correctly assembled.
  5. Position the mini float switch in the middle hole of the float bracket.
  6. Ensure the mini float switch is orientated in the normally open position, as shown in the manufacturer's diagram.
  7. Connect the float cable to the high-level alarm using the supplied crimp connectors.
  8. Test the alarm by raising the float finger. If the alarm does not sound, check the connections and test again.

The manufacturer specifies an 85dB alarm sounder. It must be located somewhere it can be heard.

Note: The manufacturer's guide also describes an alternative AquaSafe alarm. The float switch orientation differs between the HW-9 and AquaSafe arrangements. Do not use the HW-9 float orientation instructions when installing an AquaSafe alarm. Follow the relevant alarm manufacturer's documentation.

12. Electrical Installation Requirements

All electrical installation work must be carried out by a qualified electrician. The manufacturer's instructions require electrical installation to comply with the latest IET Wiring Regulations, BS 7671.

The manufacturer's guide specifies the following requirements:

  • Each mains-powered pump, battery backup system or AquaSafe alarm must be connected to its own 230V unswitched fused spur, as applicable.
  • Each unswitched fused spur must be supplied through its own dedicated, suitably rated breaker in the distribution board.
  • The pump and associated equipment must not be powered through a ring main.
  • The fused spurs should be positioned adjacent to the pump station chamber or control panels.
  • The pump fused spur must be at least 1 metre above the top of the pump station chamber.
  • Breakers must be clearly labelled to identify the connected equipment.
  • Allow sufficient cable slack to enable the pump to be removed for maintenance.
  • Keep the electrical supply isolated until the system is ready for testing.

The correct fuse and breaker ratings must be established from the manufacturer's wiring diagrams and the electrical specifications of the equipment being installed. Do not assume that every installation has identical electrical requirements.

13. Commissioning and Testing

Once the chamber, pump, pipework, alarm and electrical installation are complete, the pumping station must be commissioned in accordance with the manufacturer's instructions.

The manufacturer's installation procedure includes partly filling the chamber with clean water so that the discharge pipework can be flushed and the system tested.

Before putting the system into service, check that:

  • The chamber is clean and free from construction debris.
  • The pump is correctly connected to the internal discharge pipework.
  • The socket union O-ring is correctly seated.
  • The pump float arm can move freely without obstruction.
  • The discharge connections are secure.
  • The alarm operates correctly when tested.
  • The electrical installation has been completed and checked by a qualified electrician.

The manufacturer advises contacting Edincare Pumps if a commissioning service is required. Their technical team details are provided in the manufacturer's installation documentation.

14. Maintenance and Servicing

Regular inspection and maintenance are essential to help ensure the pumping station continues to operate correctly.

The manufacturer states that all inspection and servicing work must be undertaken by a technically qualified or competent company or engineer.

The chamber must remain permanently accessible so that the pump can be inspected, removed and serviced safely when required.

Maintenance should be undertaken in accordance with the manufacturer's recommendations and should include checks of the pump, float operation, alarm, discharge pipework and chamber condition.

Suitable safety precautions must be followed whenever work is undertaken within or around the chamber. Do not enter the chamber unless appropriate confined-space and other safety requirements have been assessed and met.


15. Wykamol Black Sump Kit – Product Options

The Wykamol Black Sump is available from Clever Shield in three product options:

  • Black Sump Lid ONLY – replacement access lid.
  • Black Sump Chamber and Lid ONLY – chamber and access lid without the complete pump kit.
  • Black Sump and Pump Kit – the complete single-pump system.

Always check the selected product variant carefully to ensure that you order the correct components for your installation.

Shop the Wykamol Black Sump Kit

16. Download the Manufacturer Installation Guide

This page is an overview of the installation process. The full manufacturer Installation and Operating Guidelines contain the detailed diagrams, permitted chamber connection positions, inlet arrangements, pipework instructions, concrete installation procedure, electrical requirements, alarm instructions, wiring diagrams and maintenance information.

Read the complete manufacturer's guide before commencing installation.

Download Wykamol Black Sump Installation and Operating Guidelines (PDF)

For further information about the product, visit the Wykamol Black Sump product page.


Important Legal Notice

This guide has been prepared by Clever Shield Coatings Ltd for general product information and guidance. Clever Shield Coatings Ltd is a supplier and distributor of waterproofing and associated products. We do not undertake site surveys, structural design, system design, installation design or project specification.

Responsibility for assessing site conditions, determining the suitability of products, designing the installation and carrying out the works rests with the relevant project professionals and installer.

All products must be selected, installed and used in accordance with the latest manufacturer technical data sheets, installation instructions and applicable regulations. Manufacturer instructions and technical documentation take precedence over this general guide.

Information on this page is provided in good faith but is not a substitute for the manufacturer's documentation or competent professional advice. Product information and manufacturer instructions may be updated, so always obtain the latest documentation before use.

To the fullest extent permitted by applicable law, Clever Shield Coatings Ltd accepts no responsibility for loss or damage arising from reliance on this general guidance, unsuitable site conditions, incorrect product selection, improper installation or failure to follow manufacturer instructions. Nothing in this notice excludes or limits any liability that cannot lawfully be excluded or limited.

For product information or assistance locating the relevant manufacturer documentation, please contact Clever Shield Coatings UK.

Newsletter

SAVE ON STRUCTURAL WATERPROOFING MATERIALS  - GET LATEST OFFERS!